土耳其卡赞天然碱矿溶采对接井质量控制措施
投稿时间:2020-07-01  修订日期:2020-07-15  点此下载全文
引用本文:张正元,涂运中,刘海翔,等.土耳其卡赞天然碱矿溶采对接井质量控制措施[J].钻探工程,2020,47(8):77-84.
ZHANG Zhengyuan,TU Yunzhong,LIU Haixiang,et al. Quality control measurements for solution mining with intersected well sets of Kazan Trona Mine in Turkey[J]. Drilling Engineering, 2020,47(8):77-84.
摘要点击次数: 1082
全文下载次数: 701
作者单位E-mail
张正元* 中国地质科学院勘探技术研究所河北 廊坊 065000 yuan1987_2007@126.com 
涂运中 中国地质科学院勘探技术研究所河北 廊坊 065000  
刘海翔 中国地质科学院勘探技术研究所河北 廊坊 065000  
刘广 中国地质科学院勘探技术研究所河北 廊坊 065000  
王万 辽宁省东煤地质103队有限责任公司辽宁 辽阳 111000  
基金项目:中国地质调查局地质调查项目“土耳其卡赞贝帕扎里天然碱矿探采方法技术合作”(编号:DD2019090602)
中文摘要:土耳其卡赞天然碱矿水溶采卤对接井施工项目技术规范中对工程质量的要求非常严格。由于矿区地质构造复杂、地层倾角大、含水层多等原因,易出现直井易斜、岩心采取率低、固井质量差,水平对接井轨迹控制难等问题。针对这些问题,在前期施工经验的基础上,通过调查研究、方案优选等手段,分别提出了针对性的措施,有效地解决了这些钻井难题,优化了钻井工艺,从而保证了施工质量,加快了施工进度。该项目钻井质量控制成果对于今后类似工程的施工具有一定的借鉴意义。
中文关键词:天然碱矿  水溶开采  水平对接井  井斜控制  固井质量  岩心采取率  土耳其卡赞碱矿
 
Quality control measurements for solution mining with intersected well sets of Kazan Trona Mine in Turkey
Abstract:The requirement on the quality control in the technical specifications is very strict for drilling of the solution mining intersected well sets at Kazan Trona Mine. The vertical wells were easily deviated, with low core recovery and poor cement bonding due to the complex geology, the high dip angle of the formation, and presence of several aquifers; meanwhile, for the horizontal well, it was very difficult to control the trajectory. After a thorough analysis of data obtained from previously drilled wells and a study of related issues and optimization of solutions, several measurements were put forward and applied. The results showed that all the drilling problems were effectively solved, the drilling process was improved, and the construction period was reduced. The experience acquired from the project could be used as reference for the similar works.
keywords:trona mine  solution mining  intersected well  deviation control of vertical well  cement bonding  core recovery  Kazan Trona Mine in Turkey
查看全文  查看/发表评论  下载PDF阅读器