中文摘要:从理论和实践对隧道开挖方法进行研究,探讨三种开挖方法,即全断面法、台阶法及导洞法的应用条件及其优点,正确选择开挖方法应考虑的主要因素。对地矿系统在隧道施工中推广新技术、新工艺和加强管理等方面提出了建议。 |
中文关键词:隧道开挖,围岩,全断面法,台阶法,导洞法 |
|
Discussion on tunnel Excavation Methods(I) |
Yaap Huilin |
Liaomng Provincial BGMR |
|
Abstract:Tunnel excawition methods have been studied from theories and practices.And conditions of usageand advantags of three methods have been discussed,these are:total cross section method,step method and guidinghole method,as well as the main factors in selecting excavating methods.Suggestions on populariring latest technolo-gy,technique and strengthenning management in tumsel excavation of MGMR have been put forward. |
keywords:tunnel excavation,to wall full-scale excavation,bench excavation, pilot-bnore excavation |