内宜高速K43+200~256段边坡治理措施 |
投稿时间:2008-11-09 点此下载全文 |
引用本文:谢元玉,刘文高,姚海平,等.内宜高速K43+200~256段边坡治理措施[J].钻探工程,2009,36(2):72-74.XIE Yuan-yu,LIU Wen-gao,YAO Hai-ping,et al. Slope Treatment Measures for Nei-Yi Expressway (K43 +200~K43 +256)[J]. Drilling Engineering, 2009,36(2):72-74. |
摘要点击次数: 1194 |
全文下载次数: 996 |
|
|
中文摘要:介绍了内宜高速公路K43+200~256段边坡的治理方案、施工措施。该边坡的4个危岩体除了都采取预应力锚索外,还针对不同危岩体的特征采取了不同的治理措施:W1预应力锚索+裂隙封填;W2预应力锚索+岩腔封砌;W3预应力锚索;W4预应力锚索+危岩体支撑。经过两年多时间的考验,证明该治理方案和措施是合理的。 |
中文关键词:危岩治理 预应力锚索 裂隙封填 岩腔封砌 危岩体支撑 |
|
Slope Treatment Measures for Nei-Yi Expressway (K43 +200~K43 +256) |
|
|
Abstract:The paper introduced slope treatment scheme and construction measures for Nei-Yi expressway (K43+200~K43+256). Besides pre-stressed anchoring cable, different treatment measures for each unstable rock mass were also applied: crack filling, rock cavity sealing and unstable rock support. It has been proved that the treatment scheme and construction measures are reasonable by time tested for more than 2 years. |
keywords:unstable rock treatment pre-stressed anchoring cable crack filling rock cavity sealing unstable rock support |