京沪高铁三标段三工区桩基施工技术探讨
投稿时间:2009-12-10  修订日期:2010-01-22  点此下载全文
引用本文:李全福.京沪高铁三标段三工区桩基施工技术探讨[J].钻探工程,2010,37(5):70-72.
LI Quan-fu. Discussion on Pile Foundation Construction Technology in 3-Contract Section of Beijing-Shanghai High-speed Railway[J]. Drilling Engineering, 2010,37(5):70-72.
摘要点击次数: 1104
全文下载次数: 992
作者单位E-mail
李全福* 中国水利水电第十工程局有限公司基础工程分局 dzlqf@vip.163.com 
中文摘要:京沪高铁项目技术标准高、工程量大、现场文明施工要求严格、施工干扰大。总结了京沪高铁三标段三工区桩基施工技术,并对灌注桩施工质量控制的几个关键环节进行了探讨。
中文关键词:桥基  钻孔灌注桩  京沪高铁
 
Discussion on Pile Foundation Construction Technology in 3-Contract Section of Beijing-Shanghai High-speed Railway
Abstract:High technical standard, large construction quantities, strict requirements on civilized construction and large construction disturbances were the characteristics of Beijing-Shanghai high-speed railway engineering. The paper summed up the pile foundation construction technology in the 3-contract section and discussed the key steps for quality control on cast-in-place pile.
keywords:bridge foundation  bored cast in place pile  Beijing-Shanghai high-speed railway