锚杆桩加固基础与掏土纠偏施工的实践 |
点此下载全文 |
引用本文:颜景忠.锚杆桩加固基础与掏土纠偏施工的实践[J].钻探工程,1994,(4):33-36.. Practice of Foundation Improvement by Anchor Piles and Deviation Correction by Soil Excavation[J]. Drilling Engineering, 1994,(4):33-36. |
摘要点击次数: 909 |
全文下载次数: 282 |
颜景忠 |
浙江有色勘察研究院 |
|
中文摘要:介绍了利用锚杆静压桩加固基础与沉井掏土纠偏方法纠治某厂房的施工过程,先用锚杆静压桩加固厂房基础,然后再用沉井掏土法纠治厂房,使偏斜率由32‰纠到了3‰的安全界限。 |
中文关键词:厂房,锚杆,加固,沉井掏土,纠偏 |
|
Practice of Foundation Improvement by Anchor Piles and Deviation Correction by Soil Excavation |
Yan Jingzhong |
Zhejiang Institute of Non- Ferrous Exploration |
keywords:factory buillding, caisson &soilexcavation,deviation correction |