顶管施工中顶力与顶程关系及其影响因素分析 |
投稿时间:2006-03-10 修订日期:2006-09-20 点此下载全文 |
引用本文:向安田,丁文其,朱合华.顶管施工中顶力与顶程关系及其影响因素分析[J].钻探工程,2006,33(10):29-31,34.. Relation between Jacking Force and Jacking Path in Pipe-packing Construction and Analysis on the Influence Factors[J]. Drilling Engineering, 2006,33(10):29-31,34. |
摘要点击次数: 952 |
全文下载次数: 1259 |
向安田 丁文其 朱合华 |
同济大学地下建筑工程系,上海200092 |
|
中文摘要:以上海某长距离急曲线顶管工程为例,通过现场实测4节管段顶进过程中的顶力,研究了顶力随顶程的变化规律,系统分析了顶进过程中顶力的主要影响因素,得到了一些有用的结论。 |
中文关键词:非开挖 顶管 顶力 顶程 变化规律 影响因素 |
|
Relation between Jacking Force and Jacking Path in Pipe-packing Construction and Analysis on the Influence Factors |
XIANG An-tian DING Wen-qi ZHU He-hua |
|
|
Abstract:In the construction of a long distance pipe-jacking tunnel with small curvature in Shanghai, jacking forces of four pipes in jacking path are measured. Based on the on- site observation,this article studies the changing pattern of jacking force in different jacking path and analyses the main influence factors to jacking force in construction, some useful conclusions are obtained. |
keywords:trenchless pipe-packing jacking force jacking path changing pattern influence factor |