CFG桩施工产生环境问题的机理分析及应对措施 |
投稿时间:2008-07-07 点此下载全文 |
引用本文:孙瑞民,杨凤灵,邓小涛.CFG桩施工产生环境问题的机理分析及应对措施[J].钻探工程,2009,36(2):24-28.SUN Rui-min,YANG Feng-ling,DENG Xiao-tao. Mechanism Analysis on Environmental Problems Caused by CFG Pile Construction and the Countermeasures[J]. Drilling Engineering, 2009,36(2):24-28. |
摘要点击次数: 1352 |
全文下载次数: 937 |
|
基金项目:河南省科技攻关项目“长螺旋钻管内泵压CFG桩复合地基技术在饱和粉土中的适应性研究”(编号:0524450008) |
|
中文摘要:根据多年施工经验,长螺旋钻管内泵压CFG桩施工技术应用到郑州地区饱和粉土等软土层时,常出现桩周地面沉降、周边建筑物和路面开裂以及管道错位等环境问题。通过对长螺旋钻管内泵压CFG桩施工引起环境问题的机理进行综合分析,提出相应措施,并对长螺旋钻管内泵压CFG桩在饱和粉土等软土层中的适应性作出评价。 |
中文关键词:CFG桩 长螺旋钻管内泵压施工 环境问题 机理分析 应对措施 适应性评价 |
|
Mechanism Analysis on Environmental Problems Caused by CFG Pile Construction and the Countermeasures |
|
|
Abstract:According to the years construction experience, when the technology of pump pressure CFG pile in continuous auger drilling pipe is applied in the stratum of saturated clay in Zhengzhou area, a series of environmental problems would come forth, such as ground settlement around piles and adjacent buildings, pavement cracking and pipeline dislocation. By the comprehensive study on the mechanism of environmental problems caused by construction of pump pressure CFG pile in continuous auger drilling pipe, the countermeasures are put forward, and the adaptability evaluation on this technology in saturated silty soil is made. |
keywords:CFG pile pump pressure construction in continuous auger drilling pipe environmental problem mechanism analysis countermeasure adaptability evaluation |