吉青岭隧道浅埋偏压进口段施工风险分析及综合防治措施
投稿时间:2009-08-19  修订日期:2009-11-26  点此下载全文
引用本文:王海明.吉青岭隧道浅埋偏压进口段施工风险分析及综合防治措施[J].钻探工程,2010,37(1):79-81,66.
WANG Hai-ming. Risk Analysis on Entrance with Shallow-buried and Unbalanced Pressure of Jiqingling Tunnel and the Measures[J]. Drilling Engineering, 2010,37(1):79-81,66.
摘要点击次数: 1174
全文下载次数: 1066
作者单位E-mail
王海明* 中铁十六局集团路桥工程有限公司 wanghm19710921@163.com 
中文摘要:结合吉青岭隧道的工程实际,分析了浅埋偏压不良地质条件下隧道进口段的施工风险,提出了采取初期支护加强,短循环开挖,初期支护封闭等综合地质病害预防措施。
中文关键词:吉青岭隧道  浅埋  偏压  进口段  风险分析  综合防治
 
Risk Analysis on Entrance with Shallow-buried and Unbalanced Pressure of Jiqingling Tunnel and the Measures
Abstract:Based on the engineering case in Jiqingling tunnel, risk analysis was made on the construction of tunnel entrance in poor geological condition with shallow-buried and unbalanced pressure. Integrated prevention measures for geological diseases were put forward with early support strengthening, short cycling excavating and early support closing.
keywords:Jiqingling tunnel  shallow-burying  unbalanced pressure  entrance  risk analysis  integrated treatment
查看全文  查看/发表评论  下载PDF阅读器