东升水电站导流墙固结灌浆施工工艺 |
投稿时间:2012-04-07 修订日期:2012-07-22 点此下载全文 |
引用本文:刘卫卫,姜鹏飞,纪晓宇,等.东升水电站导流墙固结灌浆施工工艺[J].钻探工程,2012,39(9):71-74.LIU Wei-wei,JIANG Peng-fei,JI Xiao-yu,et al. Consolidation Grouting Construction Technology for Diversion Wall in Dongsheng Hydropower Station[J]. Drilling Engineering, 2012,39(9):71-74. |
摘要点击次数: 1045 |
全文下载次数: 923 |
|
|
中文摘要:根据东升水电站导流墙固结灌浆施工实践,总结了固结灌浆过程中钻孔、裂隙冲洗、压水试验、制浆、灌浆、封孔的原则和注意事项。对灌浆过程中所遇到的漏浆及串浆特殊情况,分别采取了待凝及塞住串浆孔的措施,并取得了较好的灌浆效果。 |
中文关键词:东升水电站 固结灌浆 漏浆 串浆 |
|
Consolidation Grouting Construction Technology for Diversion Wall in Dongsheng Hydropower Station |
|
|
Abstract:According to the consolidation grouting construction for diversion wall in Dongsheng hydropower station, the paper summarizes the principles and precautions of drilling, crack flushing, water pressure test, pulping, grouting and sealing in the process of consolidation grouting. Coagulation and string slurry plugging were taken to deal with slurry leakage and string slurry in the process of grouting construction with good grouting effect. |
keywords:dongsheng hydropower station consolidation grouting slurry leakage string slurry |