基坑桩锚支护设计新方法
DOI:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

TU4

基金项目:


A NewDesign Method of Anchored Sheet Pile Wall for Excavation
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    简要讨论了用于桩锚支护设计的自由端法与固定端法中存在的问题 ,提出了一种新的设计方法。新方法在计算土压力零点以下长度时采用力平衡而不是力矩平衡的方法 ,简化了计算 ,计算结果较趋近于安全、节省的目标。给出了详细计算过程与计算实例。

    Abstract:

    The problems in the free and fixed earth support methods for thd design of the anchored sheet pile wall for excavation are briefly discussed. A new method for the design is proposed. A forces equilibrium rather than moment equilibrium method is adopted to calculate the length from the point where the stress of the soil down to zero to the bottom of the pile. The calculation is simplified by the new method, and the results approach to the goal of safety and cost saving. The details of the calculation procedures and examples to demonstrate the calculation are presented in this paper.

    参考文献
    相似文献
    引证文献
引用本文

姚爱国.基坑桩锚支护设计新方法[J].钻探工程,2000,(5):33-34,37.
YAO Ai-guo. A NewDesign Method of Anchored Sheet Pile Wall for Excavation[J]. Drilling Engineering, 2000,(5):33-34,37.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:2000-07-15
  • 录用日期:
  • 在线发布日期:
  • 出版日期: 2000-09-25