The present calculation theory of pile settlement can neither describe the complexity of the pile soil system nor meet demands in all aspects of application. To solve this problem, this paper presented a practical calculation method of piles settlement after reasonable simplifications made to the present calculation theory according to the actual facts of medium to super long bored piles. The case study shows that the method can better forecast piles settlement.