大吨位压力分散型预应力锚索生产性试验
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

TV223.34

基金项目:


Trial on Decentralized Pre-stressed Anchor Cables with Large Tonnage
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    通过江苏宜兴抽水蓄能电站工程下进出水口压力分散型锚索生产性试验,介绍压力分散型预应力锚索生产性试验过程与分析,以及通过压力分散型预应力锚索的生产性试验验证,分析锚索张拉锁定后锚索应力损失,改进施工工艺。

    Abstract:

    The decentralized pre-stressed anchor cables were tested at lower drainage outlet in Yixing Energy Storage Power Station. The test procedures were introduced and analyzed. The loss of anchor cable stress during tensing and locking was analyzed and verified by test. And the project techniques were improved though test.

    参考文献
    相似文献
    引证文献
引用本文

张俊礼,傅延舟.大吨位压力分散型预应力锚索生产性试验[J].钻探工程,2006,33(1):14-17.
ZHANG Jun-li, FU Yan-zhou. Trial on Decentralized Pre-stressed Anchor Cables with Large Tonnage[J]. Drilling Engineering, 2006,33(1):14-17.