This paper mainly introduces the reinforcement design and construction way of some high slope in Guangzhou. Various methods are used in the reinforcement program, such as anchor wire, rockbolt, anti-slide pile, steel-pipe pile, lattice girder and soil blocking wall, which have effectively raised the slope stability. The FEM method was adopted to verify the rationality of the design program. The situation results confirmed with engineering practice.
参考文献
相似文献
引证文献
引用本文
陈国勇,吴厚信,杨枫,等.广州科学城保利林语山庄高边坡支护工程的实践[J].钻探工程,2006,33(5):33-.CHEN Guo-yong, WU Hou-xin, YANG Feng, et al. Practice of High Slope Support Project in Guangzhou[J]. Drilling Engineering, 2006,33(5):33-.