球状风化孤石群内端承桩复合成孔施工技术
DOI:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Composite Construction Technology of Boring for End-bearing Pile in Spherical Weathered Boulders
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    在深圳地铁4号线403标,需要在高强度、各向异性、大倾角等特性的球状风化花岗岩孤石群地层中进行端承桩成孔,成孔与周围建筑物距离仅约20 m,且一幢建筑物已严重倾斜,鉴定判断已属于危房等级,经多次论证,最终采用对周边环境影响较小的回转钻孔工艺。先后采用刮刀钻头切削钻进、球齿滚刀钻头碾压钻进、套筒取心钻头环切纠偏等多种钻孔措施相结合的复合钻孔工艺,配以反循环泥浆护壁进行钻孔施工,取得成功。该项技术可为类似地质条件桩基成孔提供良好的技术支持。

    Abstract:

    In 403 section of Shenzhen metro Line 4, borehole should be completed for end-bearing pile in spherical weathered granite with high strength, anisotropy and large inclined angle, which was only 20m to nearby buildings, so rotary drilling was adopted for safety. Composite drilling technology of drag bit cutting drilling, button roller bit compacting and rectification by annular coring bit was adopted with wall protection by slurry reverse circulation.

    参考文献
    相似文献
    引证文献
引用本文

李福清,王元满,胡向东.球状风化孤石群内端承桩复合成孔施工技术[J].钻探工程,2009,36(1):43-48.
LI Fu-qing, WANG Yuan-man, HU Xiang-dong. Composite Construction Technology of Boring for End-bearing Pile in Spherical Weathered Boulders[J]. Drilling Engineering, 2009,36(1):43-48.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2008-07-21
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期:
  • 出版日期: 2009-01-25