汶川地震断裂带科学钻探一号孔(WFSD-1)钻探施工概况
DOI:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

P634

基金项目:

科技部科技支撑计划专项“汶川地震断裂带科学钻探(WFSD)”项目之“科学钻探与科学测井”课题


Overview on Drilling Operation of the WFSD-1 in Wenchuan Earthquake Fault Scientific Drilling Project
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    介绍了汶川地震断裂带科学钻探一号孔(WFSD-1)的施工情况以及取得的经验和教训。在施工中,克服了钻孔涌水、垮塌和地层极为破碎等困难。采用低失水、高密度和具有良好润滑性能的泥浆体系,解决了由地应力导致断层泥膨胀和缩径的技术难题。采用半合管取心技术,在破碎地层中也能获取原状性好的岩心。

    Abstract:

    This paper introduces the drilling operation of the WFSD-1 of the Wenchuan earthquake fault scientific drilling (WFSD) project as well as the experience gained and lessons learned during the hole drilling. Some extreme technical difficulties in the drilling operation, such as hole gushing water, broken formation, borehole collapse and tight hole, were overcome. A mud system with low water loss, high density and good lubrication properties was put to use to resolve mud expansion in fault gouge and diameter shrinkage resulted by geostatic stress. A twohaves tube coring technique was used to remain core in undisturbed state even in broken formation.

    参考文献
    相似文献
    引证文献
引用本文

樊腊生,贾军,吴金生,等.汶川地震断裂带科学钻探一号孔(WFSD-1)钻探施工概况[J].钻探工程,2009,36(12):5-8.
FAN La-sheng, JIA Jun, WU Jin-sheng, et al. Overview on Drilling Operation of the WFSD-1 in Wenchuan Earthquake Fault Scientific Drilling Project[J]. Drilling Engineering, 2009,36(12):5-8.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2009-11-23
  • 最后修改日期:2009-11-23
  • 录用日期:2009-11-23
  • 在线发布日期: 2010-01-11
  • 出版日期: 2009-12-25