Groundwater pump and re-injection in the same well is mainly applied in shallow geothermal development. For GSHP system, the proportion between pump well and re-injection wells is 1∶3~1∶6, for fine particle formation, it not only means more construction cost, but also means large site area, management inconvenience and difficult re-injection. According to the analysis and research, “pump and re-injection in the same well” system was designed according to the drilling theory and hydrogeology conditions, pump and re-injection in the same well was realized with satisfied effects. The paper explained “pump and re-injection in the same well” about equipment selection, well completion technology and application effect.
参考文献
相似文献
引证文献
引用本文
吴烨,卢予北,牛建设,等.地下水同井抽回井施工技术与应用研究[J].钻探工程,2011,38(9):33-36.WU Ye, LU Yu-bei, NIU Jian-she, et al. Construction Technology and Application Research in Groundwater Pump and Re-injection in Same Well[J]. Drilling Engineering, 2011,38(9):33-36.