铜多金属矿帷幕注浆堵水方案研究
DOI:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

TD743

基金项目:


Scheme Study on Curtain Grouting for Water Blocking in Copper Polymetallic Deposit
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    结合江西乐平市月形铜多金属矿帷幕注浆堵水工程,主要阐述了矿山发生涌水灾害后治理的方法选择及治理工序,并对注浆法的施工工艺加以研究和推广,同时简单介绍了施工过程中一些常见问题及处理对策。根据该工程的工程地质条件、工程性质、预算等限制条件选择高压孔内循环式注浆;下行式分段注浆方式方法。浆材为水泥粉煤灰和水泥粘土浆两种,必要时加入适量水玻璃。最后,通过钻心、压水对比和面波检测确定注浆是否达到工程要求。

    Abstract:

    According to the engineering of curtain grouting for water control in Yuexing copper polymetallic deposit of Jiangxi, the paper described the selection of treatment methods and the treatment process, the grouting construction technology was studied and promoted; briefly introduced some common problems in construction process with countermeasures. Based on the restricting conditions such as engineering geological conditions, engineering properties and the budget, high-pressure hole with internal circulation grouting and downward stage grouting were selected. The grouting material were cement fly-ash and cement clay grout, water glass grout could be added while necessary. The engineering quality was determined by drilling coring, water pressure test and surface wave detection.

    参考文献
    相似文献
    引证文献
引用本文

李万全,夏焰光.铜多金属矿帷幕注浆堵水方案研究[J].钻探工程,2012,39(1):68-72.
LI Wan-quan, XIA Yan-guang. Scheme Study on Curtain Grouting for Water Blocking in Copper Polymetallic Deposit[J]. Drilling Engineering, 2012,39(1):68-72.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2011-07-29
  • 最后修改日期:2011-07-29
  • 录用日期:2011-11-03
  • 在线发布日期: 2012-01-10
  • 出版日期: 2012-01-25