    结合中平能化集团某矿大口径输冰井的工程实践,总结了大口径输冰井的施工技术。从设备机具的选择,先导孔及扩孔钻具组合,采用先导孔、分级扩孔和水泥固井方法等方面阐述了大口径输冰井钻井施工中的相关技术措施以及研制的新型保温套管和采用割孔穿杠提吊加浮力塞的下套管方法。

    Abstract:

    With the engineering practice of the large diameter ice transmission well of a coalmine, the construction technologies of large diameter ice transmission well were summed up. The relative technologies in the drilling construction were discussed about the equipment selection, bottom hole assembly for pilot hole & reaming, the pilot hole, step reaming and well cementing; and the newly developed insulating case and casing method by lifting bar in cutting-holes and floating plug were also presented.

    参考文献
    相似文献
    引证文献
引用本文

缑延民.煤矿大口径输冰井施工技术[J].钻探工程,2012,39(8):69-71,84.
GOU Yan-min. Construction Technology of Large Diameter Ice Transmission Well in Coalmine[J]. Drilling Engineering, 2012,39(8):69-71,84.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2012-07-16
  • 最后修改日期:2012-07-16
  • 录用日期:2012-07-31
  • 在线发布日期: 2012-08-30
  • 出版日期: