    摘要:

    针对黄陵矿业公司运煤铁路专用线新庄科隧道西出口边坡崩塌、落石灾害发育的特点,提出采用喷射砼面层防止岩层表面进一步风化、采用预应力锚索框架梁防止山体发生崩塌灾害的治理设计方案,并根据设计对边坡进行了治理施工。介绍了治理方案设计及施工要点。

    Abstract:

    According to the slope collapse and rock falling in a tunnel of coal special railway line in Huangling mining company, the control plan was put forward by concrete spraying and pre-stressed cable frame beam to prevent the further weathering of the rock surface and the mountain collapse. The control construction was carried out based on the design the paper introduces the control plan design and the main points of the construction.

    参考文献
    [1]GB50330-2002,建筑边坡工程技术规范[S]
    [2].谭彬建,俞敏,息飏,黄定平.桂柳高速公路边坡预应力锚索加固方案设计[J].探矿工程(岩土钻掘工程),2010,37(5):73-77.
    [3].黄健民,李德洲.河梅高速公路某边坡加固支护施工技术[J].探矿工程(岩土钻掘工程),2005,32(6):31-33.
    [4].刘以波,穆道贵,潘金禄,刘波.已通车高速公路路堤滑坡处治方案设计与施工[J].探矿工程(岩土钻掘工程),2002,(6):7-9.
    [5].陕西地质工程总公司,黄陵矿业集团铁路专用线新庄科隧道西出口加固工程设计[R],2013.03.
    网友评论
    网友评论
    分享到微博
    发 布
引用本文

张丽红,王振福.黄陵矿业公司运煤专线边坡治理方案设计与施工[J].钻探工程,2013,40(9):55-58.
ZHANG Li-hong, WANG Zhen-fu. Design of the Slope Treatment Plan for Coal Special Railway Line of Huangling Mining Company[J]. Drilling Engineering, 2013,40(9):55-58.

复制
分享
文章指标
  • 点击次数:1039
  • 下载次数: 897
  • HTML阅读次数: 219
  • 引用次数: 0
历史
  • 收稿日期:2013-06-17
  • 最后修改日期:2013-08-19
  • 录用日期:2013-08-31
  • 在线发布日期: 2013-10-08
文章二维码