Technical control and drilling of standard geo-technicalinvestigation boreholes in the Xiongan New Area
Author:
Affiliation:

1.Hebei Bureau of Geology and Mineral Resources Exploration, Shijiazhuang Hebei 050081, China;2.Territorial Resources Exploration Center of Hebei Geo-mineral Bureau, Shijiazhuang Hebei 050081, China

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    雄安新区地质勘察大会战中200 m标准勘察钻孔,地层层位交替变化大,局部夹软弱地层和砂土液化,砂类地层胶结性差、结构松散等,难以保证垂直度以及岩心采取率。施工中采用了合理钻具配置、优化钻进参数等综合措施,预防钻孔偏斜;同时在取心时采用松散地层干钻取心、岩心管内隔离措施、采用泥浆泵分流注浆退心等行之有效的技术措施,保证了钻孔质量,取得了非常明显的技术效果。

    Abstract:

    In order to cope with the difficulty in maintaining the borehole verticality and core recovery due to great alternation of strata, liquefaction of soft strata and sand, poor cementation and loose structure of sand encountered in drilling of the standard 200m geo-technical investigation boreholes in the Xiongan New Area, comprehensive measures such as proper configuration of the drilling string, optimization of drilling parameters have been adopted to prevent drilling deviation. At the same time, effective technical measures such as dry core drilling in loose strata, isolation in core barrels, diversion of the mud pump discharge for core ejection have been adopted to ensure the drilling quality, leading to very obvious technical results.

    参考文献
    相似文献
    引证文献
引用本文

李忠,和新,李艳丽,等.雄安新区工程地质勘察标准钻孔技术控制及施工实践[J].钻探工程,2019,46(5):8-12.
LI Zhong, HE Xin, LI Yanli, et al. Technical control and drilling of standard geo-technicalinvestigation boreholes in the Xiongan New Area[J]. Drilling Engineering, 2019,46(5):8-12.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2018-11-07
  • 最后修改日期:2019-04-16
  • 录用日期:2019-04-16
  • 在线发布日期: 2019-05-17
  • 出版日期:
文章二维码