Discussion on Construction Technology of Long Pipe-shed Pre-reinforcement for Tunnel and Feature Requirement of Drilling Machine
DOI:
Author:
Affiliation:

Clc Number:

U455.4

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    With the construction case of 65 m long pipe-shed pre-reinforcement, the paper introduced the construction technology of long pipe-shed whh Haiwangxing - 508 drilling machine, and discussed the feature requirement of drilling machine in the construction.

    Reference
    Related
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:May 30,2007
  • Revised:August 17,2007
  • Adopted:
  • Online:
  • Published: