Abstract:The paper discussed and analyzed an important parameter—build-up intensity (the drift angle’s change of drilling hole in one meter length drilling, degree/meter) which influences the hole section designed. It has established the build-up intensity model through the whole stress analysis on drilling tool and has obtained the formula of build-up intensity affected by the resistance of soil and the curve of drilling tool in the preliminary stage of angle building. Then it analyzes the primary factors that affect the buildup intensity in the basis of formula and has got some conclusions. This paper also gives qualitative explanation on the rule of continuous buildup intensity by indoor tests.