Experimental Application of Deviation Control Technologies in Xuanye Well 1
DOI:
CSTR:
Author:
Affiliation:

Clc Number:

TE242

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    As an exploration well, Xuanye Well 1 was designed 2570m in vertical depth for shale gas resource potential evaluation. The construction was mainly drilling in the Mesozoic-Paleozoic formation with dense lithology, drillability extreme of 8~10 and formation tip about 45. Based on the analysis on the technology and the mechanism of deviation control with tower-type drilling tool, eccentric drilling tool, compound drilling and vertical well drilling; the paper introduced the experimental application of all kinds of deviation control technologies in Xuanye Well 1, and the application effects of all kinds of deviation control technologies were evaluated.

    Reference
    Related
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:November 29,2010
  • Revised:November 29,2010
  • Adopted:February 21,2011
  • Online: May 27,2011
  • Published: May 25,2011
Article QR Code