Test of Pile Bottom Post Grouting for Super Long Pile in Sutong Bridge and the Effect
DOI:
CSTR:
Author:
Affiliation:

Clc Number:

U443.15+4

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    Pile bottom post grouting for friction pile with super long (>100m) and super large(φ2.5m)was first applied in loose and soft formation in Sutong Bridge construction in China. Based on the engineering practice, the design and key technical points were introduced. By the analysis on the samples, the obvious difference of slurry initial setting time between ground experiment and underground situation was found. According to the slurry diffusion and permeation conditions by sampling, the grouting amount, not the pressure, is taken as control parameter in permeable formation.

    Reference
    Related
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:July 29,2011
  • Revised:November 06,2011
  • Adopted:November 07,2011
  • Online: November 29,2011
  • Published:
Article QR Code