Pre-stressed Anchor Super-Grouting Control Technique in Lianghekou Hydropower Station
DOI:
Author:
Affiliation:

Yalong River Hydropower Development Company Ltd.,Yalong River Hydropower Development Company Ltd.

Clc Number:

P642.22; TV54

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    The local geological conditions are strong weathered, strong unloading anti-dip thin layer-middle-thick layer sand slate with joints and fractures developing, broken surrounding rocks, open fissures and serious loose unloading in road slope excavation at Lianghekou hydropower station. The frame beams and non-cohesive steel strand dispersion-type pre-stressed anchorage cable were designed to reinforce the side slope. The paper describes the super grouting control technique for pre-stressed anchor grouting in poor geological conditions.

    Reference
    Related
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:October 08,2012
  • Revised:November 26,2012
  • Adopted:February 18,2013
  • Online: March 25,2013
  • Published: