Advanced Drilling Exploration for Foundation Pile Engineering in Karst Region and the Optimization Design
DOI:
CSTR:
Author:
Affiliation:

No.5 Geological Party, Jiangsu Bureau of Geology and Mineral Exploration,China Resources Power 〈Hezhou〉 Co., Ltd.,China Resources Power 〈Hezhou〉 Co., Ltd.,Tangshan China Resources Thermal Power Co., Ltd.,No.5 Geological Party, Jiangsu Bureau of Geology and Mineral Exploration

Clc Number:

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    Foundation treatment is one of the most important steps in the power plant construction, and is also a basic work,especially in the karst region, where the geological conditions are more complicated. Analysis is made on the technical problems in the engineering pile construction of Hezhou power plant, according to the karst geological conditions of the corrosion belt, combined with the karst fissures, karst ditches, grooves and caves, the construction technical difficulties and measures are briefly analyzed.

    Reference
    Related
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:January 23,2013
  • Revised:June 10,2013
  • Adopted:July 02,2013
  • Online: September 03,2013
  • Published:
Article QR Code