Directional Blasting Demolition of a 120m Chimney in Complex Environment
DOI:
Author:
Affiliation:

Guangdong Zhongren Blasting Engineering Co.,Ltd,Guangdong Zhongren Blasting Engineering Co.,Ltd,Guangdong Zhongren Blasting Engineering Co.,Ltd

Clc Number:

TU746.5

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    The design and construction of directional blasting demolition of a 120m high chimney in Changzhou is introduced, where existing hot gas pipeline, workshop, communication tower and high voltage line and so on. The environment of blasting area is complex and near to the protection objects, it is difficult to control the collapse vibration and flyrocks. According to the features of chimney structure and the site actual situation, good blasting results are achieved by rising the blasting cut height, selecting reasonable design scheme and parameters and adopting pertinence safety precautions measures of damping ditch, damping earth embankment and cut-off wall.

    Reference
    Related
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:July 06,2017
  • Revised:November 08,2017
  • Adopted:November 23,2017
  • Online: February 27,2018
  • Published: