Dry rotary borehole drilling and quality control in the karst area
CSTR:
Author:
Affiliation:

China Solibase Engineering Co., Ltd.

Clc Number:

TU473

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    In the construction of pile foundation at the Panzhou Station of the Shanghai-Kunming Railway, the rotary drill rig was used to dry-drill the holes, and dissolved caves were encountered in drilling of nearly 1/3 the foundation piles. Based on the analysis of different adverse situations, and according to the geological conditions of unfilled and semi-filled karst caves encountered, specific technical measures were adopted, including wall construction by backfilling soil and stone and compaction by reverse rotation, sinking boreholes section by section by squeezing plain concrete, protection of borehole walls and retaining of pile concrete with casing, leveling of uneven rock surface and re-drilling, point-backfilling and cementation; as a result, the pile foundation was successfully completed.

    Reference
    Related
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:April 08,2019
  • Revised:December 15,2019
  • Adopted:December 16,2019
  • Online: January 15,2020
  • Published:
Article QR Code