Application of multi-process combined well flushing and pumping test in Well CGSD-01
DOI:
Author:
Affiliation:

1.The Institute of Exploration Techniques, CAGS, Langfang Hebei 065000, China; 2.Center for Hydrogeology and Environmental Geology, CGS, Baoding Hebei 071051, China

Clc Number:

P634;TE249

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    The well CGSD-01 of Donglihu in Tianjin is a geothermal exploration well. The design depth of the well is 4000m and the completion depath is 4051.68m. In order to clean up the blockage of aquifer in the drilling process, the well is flushed by three methods, and pumping tests are carried out twice. This paper mainly describes the well washing and pumping test technology and process of the well CGSD-01, in order to provide useful reference for similar research in the future.

    Reference
    Related
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:April 18,2019
  • Revised:May 21,2019
  • Adopted:May 21,2019
  • Online: June 20,2019
  • Published: