    Abstract:

    In view of much time consumption and high risk in pile hole construction for signal tower foundations by the manual water grinding drill combined with air pick in mountainous areas in China, the market is in urgent need of a kind of equipment which can reduce the labor intensity, has high safety factor and fast cutting speed, and is portable and modular. At present, the commonly used foundation pile drilling equipment on level ground mainly includes: shaft drilling machines, raise boring machines and shaft boring machines, etc. These equipment is featured of heavy weight and large overall dimension, difficult handling and poor adaptability to complex terrain and mountainous conditions. To this end, the YXW-2000 hydromill has been developed. It can effectively improve the mechanization degree of pile hole construction in mountainous areas, reduce the labor intensity of workers, and improve the safety of equipment operation. This paper mainly introduces the main technical parameters, the structural layout characteristics and the hydraulic system of the hydromill. The test results showed that YXW-2000 hydromill can meet the mechanization requirements of drilling construction with ease in disassembly and convenient handling, and has a good application prospect.

    Reference
    [1] 鲁先龙,程永锋.我国输电线路基础工程现状与展望[J].电力建设,2005,26(11):25-27,34.LU Xianlong, CHENG Yongfeng. Current status and prospect of transmission tower foundation engineering in China[J]. Electric Power Construction, 2005,26(11):25-27,34.
    [2] 方月舵,郑卫锋,叶超,等.输电线路岩石嵌固基础选型及施工技术研究[J].电力勘测设计,2017(5):10-14.FANG Yueduo, ZHENG Weifeng, YE Chao, et al. Type selection and construction technology of rock embedded foundation in transmission line[J]. Electric Power Survey & Design, 2017(5):10-14.
    [3] 蔡连杰.大型竖井钻机主动式导向器研究[D].淮南:安徽理工大学,2013.CAI Lianjie. Research on active guiding device of large shaft drill[D]. Huainan: Anhui University of technology, 2013.
    [4] 刘志强,甘文鸿.反井钻机技术与地下工程开发[J].地下空间,1999,19(4):425-428.LIU Zhiqiang, GAN Wenhong. Raise boring machine technology and underground engineering development[J]. Underground Space. 1999,19(4):425-428.
    [5] 牛庆磊,吕永亮,贾炜,等.旋挖钻机配套集束式潜孔锤硬岩施工方法研究[J].探矿工程(岩土钻掘程),2015,42(12):57-60.NIU Qinglei, Yongliang LÜ, JIA Wei, et al. Study on hard rock drilling construction by rotary drilling rig matched with cluster DTH hammer[J]. Exploration Engineering (Rock & Solid Drilling and Tunneling), 2015,42(12):57-60.
    [6] 张化民.大口径旋挖碎岩机理研究及钻具设计[D].成都:成都理工大学,2013.ZHANG Huamin. Large diameter rotary drilling rock fragmentation mechanism research and drilling tool design[D]. Chengdu: Chengdu University of Technology, 2013.
    [7] 徐用超.输电线路岩石基础开挖方法的比较[J].建筑工程技术与设计,2017(20):1445-1446.XU Yongchao. Comparison of excavation methods for rock foundation of transmission line[J]. Architectural Engineering Technology and Design, 2017(20):1445-1446.
    [8] 陈长生.水磨钻机开挖输电线路岩石基础[J].城市建设理论研究(电子版),2015(7):1121-1122.CHEN Changsheng. Excavation of transmission line rock foundation with water mill drill[J]. Theoretical Research on Urban Construction (Electronic Version), 2015(7):1121-1122.
    [9] 高进军.水磨钻人工挖孔施工技术的应用[J].浙江建筑,2015(2):23-26.GAO Jinjun. Application of the construction technology of hand-dugging by water-mill drilling[J]. Zhejiang Construction, 2015(2):23-26.
    [10] 陈礼仪,宋刚,于好善,等.动静组合加载下刀具破岩的力学模型[J].探矿工程(岩土钻掘工程),2013,40(2):15-18.CHEN Liyi, SONG Gang, YU Haoshan, et al. Mechanical analysis on rock fragmentation under combined static and dynamic loading[J]. Exploration Engineering (Rock & Solid drilling and Tunneling), 2013,40(2):15-18.
    [11] 张祖培,刘宝昌.碎岩工程学[M].北京:地质出版社,2004.ZHANG Zupei, LIU Baochang. Rock Crushing Engineering[M]. Beijing: Geological Publishing House, 2004.
    [12] 徐小荷,余静.岩石破碎学[M].北京:煤炭工业出版社,1981:20-45.XU Xiaohe, YU Jing. Rock Fragmentation[M]. Beijing: Coal Industry Press, 1981:20-45.
    [13] 闻邦椿.机械设计手册[M].北京:机械工业出版社,2010:100-200.WEN Bangchun. Mechanical Design Manual[M]. Beijing: China Machine Press, 2010:100-200.
    [14] 江耕华.机械传动设计手册(上下册)[M].北京:煤炭工业出版社,1992:35-75.JIANG Genghua. Mechanical Transmission Design Manual (Volume One and Volume Two)[M]. Beijing: Coal Industry Press, 1992:35-75.
    [15] 许贤良.液压传动[M].北京:国防工业出版社,2011:27-35.XU Xianliang. Hydraulic Transmission[M]. Beijing: National Defense Industry Press, 2011:27-35.
    [16] 何存兴.液压元件[M].北京:机械工业出版社,1982:15-35.HE Cunxing. Hydraulic Components[M]. Beijing: China Machine Press, 1982:15-35.
    [17] 臧克江.液压缸[M].北京:化学工业出版社,2010:50-80.ZANG Kejiang. Hydraulic Cylinder[M]. Beijing: Chemical Industry Press, 2010:50-80.
    [18] 雷天觉.新编液压工程手册[M].北京:机械工业出版社,1998:125-300.LEI Tianjue. New Handbook of Hydraulic Engineering[M]. Beijing: China Machine Press, 1998:125-300.
    [19] 刘家荣.复杂地层桩孔钻进工艺及机具研究[D].北京:中国地质大学(北京),2010.LIU Jiarong. Research on pile hole drilling technology and tools in complex strata[D]. Beijing: China University of Geosciences (Beijing), 2010.
    [20] 宋刚.硬岩地层旋挖钻进组合工艺的研究与应用[J].施工技术,2011,40(2):72-74.SONG Gang. Application and research on combinatory rotary drilling process in hard rock[J]. Construction Technology, 2011,40(2):72-74.
    [21] 刘三意.多工艺旋挖钻进技术研究[D].北京:中国地质大学(北京),2008.LIU Sanyi. Research on multi process rotary drilling technology[D]. Beijing: China University of Geosciences (Beijing), 2008.
    Related
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:600
  • PDF: 843
  • HTML: 831
  • Cited by: 0
History
  • Received:May 10,2021
  • Revised:February 11,2022
  • Adopted:November 29,2021
  • Online: December 05,2022
  • Published: November 10,2022
Article QR Code