Comparative analysis of fuel consumption of 360 rotary drilling rig in drilling of foundation piles at different diameters
Author:
Affiliation:

Second Team of Hunan Nonferrous Metals Geological Exploration Bureau, Hengyang Hunan 421001, China

Clc Number:

P634.3

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    In regard to the pile foundation excavation works of the Lot 1 Guanyinyan Interchange Bridge Project of the Changsha-Yiyang Section Expressway Expansion Project, study was conducted on the oil consumption of a 360 rotary drilling rig in the construction of different diameter pile foundations in this project with consideration of pile diameter, pile length, pile number, engineering quantity, and consumption oil ratio and other factors,, and analysis was made on the causes for the different mechanical oil consumption due to different pile parameters. It was concluded that the pile diameter is the key factor for the increase of mechanical fuel consumption, which has certain guiding significance for the selection of machinery in the pile foundation excavation project and the cost estimation.

    Reference
    Related
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:July 07,2021
  • Revised:July 07,2021
  • Adopted:July 14,2021
  • Online: December 06,2021
  • Published: September 01,2021